Jakarta International Stadium Construction Accelerated

The process of Jakarta International Stadium (JIS) construction project has touched 38.69 percent.

We are currently completing the pierhead in the main column

Corporate Communication & Commercial for JIS Project, Arnold Kindangen mentioned, entering the 66th week, its process has touched 38.69 percent. It has entered the finishing stage of east ramp and roof structure assembling.

"We are currently completing the pierhead in the main column. The construction uses slipform concept," he conveyed, Wednesday (12/9).

Entering 64th Week, JIS Construction Touches 36.7 Percent

For construction on the training field, he continued, is still in the finishing stage for stands and lamppost installation.

"JIS area in total reaches 23 hectares with land under RAP of 1.2 hectares," he stated.

According to him, JIS area is expected to reach 235,127 square meters with audience capacity of 82,000 people.

Linked News
Popular News indeks
  1. Waste Sorting Education Given for 500 Students of SDN 07

    access_time26-04-2024 remove_red_eye746 personAnita Karyati
  2. 37.25 Ton of Campaign Prop Waste in West Jakarta Recycled

    access_time26-04-2024 remove_red_eye508 personTP Moan Simanjuntak
  3. LRT Phase 1B Construction Remains Positive

    access_time27-04-2024 remove_red_eye435 personAldi Geri Lumban Tobing
  4. East Jakarta Sudinhub Replaces 38 Broken Convex Traffic Mirrors

    access_time26-04-2024 remove_red_eye383 personNurito
  5. 81 Pets in West Jakarta Get Anti Rabies Vaccine

    access_time26-04-2024 remove_red_eye379 personTP Moan Simanjuntak